…02…PC/TRP/0003
…02…BHE/831229…02……02…#
PROTOCOL CONVERTER
FACTORY ACCEPTANCE TEST REPORT, SITE 3…02……02… PC
PROTOCOL CONVERTER
FACTORY ACCEPTANCE TEST
REPORT, SITE 3
PC/TRP/0003
Line Item No. 1.14
B]rge Hermansen
B[RGE HERMANSEN
SHAPE (2), DL.
…0f…
1
831229
PC/TRP/0003
…02…BHE/831229…02… ii
PROTOCOL CONVERTER
FACTORY ACCEPTANCE TEST REPORT, SITE 3…02… …02… PC
…0f…
831229 All Initial issue of
Document
…02…PC/TRP/0003
…02…BHE/831229…02… iii
PROTOCOL CONVERTER
FACTORY ACCEPTANCE TEST REPORT, SITE 3…02… …02… PC
TABLE OF CONTENTS
1 GENERAL ..........................................
1
1.1 PURPOSE ......................................
1
1.2 APPLICABLE DOCUMENTS .........................
1
2 TEST OVERVIEW ....................................
1
2.1 CONTRACTUAL REFERENCES .......................
1
2.2 TEST BASELINE ................................
2
3 TEST GROUND RULES ................................
2
4 TEST CONDUCTORS ..................................
3
A̲P̲P̲E̲N̲D̲I̲C̲E̲S̲
APP. A: PROTOCOL CONVERTER ACCEPTANCE TEST
PROCEDURES, SITE 2, (PC/TPR/0001(2.2))
SEC. 2
APP. B: TEST LOG, PC SITE 3
SEC. 3
APP. C: CONFIGURATION LIST 831224
SEC. 4
APP. D: FAT-APPLIED MESSAGES
SEC. 5
APP. E: RELATED COMPUTER PRINTOUTS G.F.C. 4.5.3
SEC. 6
APP. F: RELATED COMPUTER PRINTOUTS G.F.C. 4.5.4
SEC. 7
1 G̲E̲N̲E̲R̲A̲L̲
1.1 P̲U̲R̲P̲O̲S̲E̲
The purpose of this document is to describe the result
of the SITE 3 Factory Acceptance Test, which took place
at the Christian Rovsing A/S facilities on 831215 and
831228.
1.2 A̲P̲P̲L̲I̲C̲A̲B̲L̲E̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲S̲
a) Protocol Converter Test Plan
Contract SHNMO-82-9205-INF.
PC/TPL/001, issue 3.
b) Protocol Converter Acceptance Test Procedures
Contract SHNMO-82-9205-INF.
PC/TPR/001, issue 2.2.
2 T̲E̲S̲T̲ ̲O̲V̲E̲R̲V̲I̲E̲W̲
2.1 C̲O̲N̲T̲R̲A̲C̲T̲U̲A̲L̲ ̲R̲E̲F̲E̲R̲E̲N̲C̲E̲S̲
On the dates of 15 and 28 of November, 1983, the
Site 3 Factory Acceptance Test was completed successfully.
The test is specified in the Protocol Converter Test
Plan para's 3.3.2 to 3.3.2.6 and the Protocol Converter
Contract Clause 14.3.
2.2 T̲E̲S̲T̲ ̲B̲A̲S̲E̲L̲I̲N̲E̲
The Factory Acceptance Test Report (this document)
is divided into 7 sections:
1. Protocol Converter Factory Acceptance Test Report,
Site 3,
PC/TRP/0002(1).
2. Protocol Converter Acceptance Test Procedures,
Site 3,
PC/TPR/0001 (2.2) App. A.
3. Test Log, PC Site 3. App. B.
4. Configuration List 831215 App. C.
5. FAT-APPLIED MESSAGES App. D.
6. RELATED COMPUTER PRINTOUTS G.F.C. 4.5.3 App. E.
7. RELATED COMPUTER PRINTOUTS G.F.C. 4.5.4 App. F.
3 T̲E̲S̲T̲ ̲G̲R̲O̲U̲N̲D̲ ̲R̲U̲L̲E̲S̲
The Site 3 FAT was based on the sequences of tests
described in the test procedures in the document "Protocol
Converter Acceptance Test Procedures, Site 3, PC/TPR/0001(2.2).
During the tests, the results was noted in the test
procedure and the test log. If any comments were necessary,
these were noted in the test procedure and test log
as well.
If a problem was encountered during the test, the problem
was either catagorised as a descrepancy or a defect.
By a descrepancy is meant a mutually agreed issue showing
an agreed date for clearance of the issue. By a defect
is meant a problem which prevented the acceptance of
the test.
Also problems encountered during the test were divided
into two further categories:
o Board Failures
o System Level Failures.
Board failures were corrected immediately by replacement
of the board. System level failures were corrected
after the first test was completed and a retest was
performed.
4 T̲E̲S̲T̲ ̲C̲O̲N̲D̲U̲C̲T̲O̲R̲S̲
The following test team conducted the test:
[strup, Thorvald SHAPE Representative (GQAR)
Hermansen, Boerge PC Program Manager
Holgersen, Erik PC S/W Engineer
Plesner, Kenneth PC S/W Engineer
Larsen, Djon PC H/W Engineer
Strandtoft, Benny CR QA S/W
Villadsen, Erik CR QA H/W
CR QA maintained the official copy of the test results.