⟦e27f25292⟧ Wang Wps File

    Length: 5523 (0x1593)
    Types: Wang Wps File
    Notes: CAMPS Install. Planning   
    Names: »3468A «

Derivation

└─⟦4fd1db2d6⟧ Bits:30006202 8" Wang WCS floppy, CR 0295A
    └─ ⟦this⟧ »3468A « 

WangText




…02… 3468A/ktd 

…02… KM/830324…02……02…#
CAMPS INSTALLATION PLANNING
…02……02…CAMPS























                  Her inds`ttes tegning



































             CAMPS TYPICAL INSTALLATION PLAN



         C̲A̲M̲P̲S̲ ̲T̲Y̲P̲I̲C̲A̲L̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲P̲L̲A̲N̲

         The following contains a brief description of the installation
         operations listed on the CAMPS Installation plan:

         1   T̲r̲a̲v̲e̲l̲t̲i̲m̲e̲

         2   A̲r̲r̲i̲v̲a̲l̲/̲I̲n̲t̲r̲o̲d̲u̲c̲t̲i̲o̲n̲

         3   M̲e̲c̲h̲a̲n̲i̲c̲a̲l̲ ̲R̲a̲c̲k̲ ̲A̲s̲s̲e̲m̲b̲l̲y̲

             The equipment racks (Rack A-G) will after arrival
             to the site be moved to the CAMPS equipment area
             and unpacked. The racks will be aligned and bolted
             together to form the 3-bay computer unit (Rack
             A-B-C) and the 4-bay line termination unit (Rack
             D-E-F-G).

             The Freq. Stabilizer will be moved to its position
             and integrated.

             The TARE rack will be moved into the encryption
             area and integrated.

             All terminals and the terminal tables will be distributed
             to their respective installation sites.

         4   E̲x̲t̲e̲r̲n̲a̲l̲ ̲P̲o̲w̲e̲r̲ ̲C̲a̲b̲l̲e̲s̲

             The power cables coming from the CAMPS power distribution
             board will be terminated in the Frequency Stabilizer
             and the power line filters of Rack A, B, and E.

         5   E̲x̲t̲e̲r̲n̲a̲l̲ ̲S̲i̲g̲n̲a̲l̲ ̲C̲a̲b̲l̲e̲s̲

             Opto fibre cables coming from the user terminals
             entering rack D through the CR installed conduits
             will be distributed to their respective termination
             points in racks C, D, and E.

             Cables from rack D to the supervisory and maintenance
             positions will be installed.



             All metallic cables coming from the customer delivered
             LSM terminals as well as the metallic cables coming
             from other connections (e.g. SCARS, CCIS, etc)
             will be installed in the filter box of rack F through
             the CR installed metallic conduit.

             Interrack cables between the computer and line
             termination units will be installed.

         6   I̲n̲t̲e̲r̲n̲a̲l̲ ̲S̲i̲g̲n̲a̲l̲ ̲C̲a̲b̲l̲e̲s̲

             All internal signal cables in the computer and
             line termination units, disconnected for the transportation,
             will be reinstalled. Cables not dismounted will
             be checked for being properly connected.

         7   T̲e̲r̲m̲i̲n̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲E̲x̲t̲e̲r̲n̲a̲l̲ ̲S̲i̲g̲n̲a̲l̲ ̲C̲a̲b̲l̲e̲s̲

             All opto fibre cables to be connected on front
             of the line termination unit (racks D, E and G)
             will be terminated with special opto connectors.

             Metallic interface cables to be connected in the
             filterbox of rack F are to be terminated by customer.

         8   R̲e̲m̲o̲t̲e̲ ̲T̲A̲R̲E̲ ̲S̲i̲t̲e̲ ̲A̲

             The TARE rack at the remote TARE site will be integrated
             and connected. An end to end test between the TARE
             racks at the main and remote site will be performed.

         9   I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲R̲e̲m̲o̲t̲e̲ ̲T̲e̲r̲m̲i̲n̲a̲l̲s̲ ̲S̲i̲t̲e̲ ̲A̲

             The user terminals at CRT A will be installed and
             connected to the stat. mux. rack.

             A local test will be performed.

         10  R̲e̲m̲o̲t̲e̲ ̲T̲A̲R̲E̲ ̲S̲i̲t̲e̲ ̲B̲

             A test between the TARE rack at the main and the
             remote site will be performed.




         11  I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲R̲e̲m̲o̲t̲e̲ ̲T̲e̲r̲m̲i̲n̲a̲l̲s̲ ̲S̲i̲t̲e̲ ̲B̲

             The user terminals at CRT B will be installed and
             connected to the stat. mux. rack.

             A local test will be performed.

         12  I̲n̲t̲e̲r̲n̲a̲l̲ ̲P̲o̲w̲e̲r̲ ̲C̲a̲b̲l̲e̲s̲

             All internal power cables disconnected for transportation
             will be reinstalled in the computer and line termination
             unit.

         13  I̲n̲s̲t̲a̲l̲l̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲T̲e̲r̲m̲i̲n̲a̲l̲s̲

             All opto fibre cables for the User-, Maintenance-,
             and Supervisory Terminals will be terminated with
             special opto connectors. Before connecting the
             cables to the optical modem boards, they will be
             checked for adequate light emission.

             The terminals will be powered up and tested locally.

         14  P̲o̲w̲e̲r̲ ̲U̲p̲ ̲a̲n̲d̲ ̲T̲e̲s̲t̲

             Powering up the computer and line termination units
             will be performed in a certain sequence in order
             to check that power groups and phases are correctly
             distributed.

             To ensure that the hardware will be able to support
             all required CAMPS functions, a functional test
             will be carried out according to the specified
             site verification procedure.

         15  T̲e̲s̲t̲ ̲o̲f̲ ̲T̲e̲r̲m̲i̲n̲a̲l̲s̲

             All installed terminals including the PTP/PTR will
             be tested according to the site acceptance test
             procedure.

         16  T̲e̲s̲t̲ ̲o̲f̲ ̲R̲e̲m̲o̲t̲e̲ ̲T̲e̲r̲m̲i̲n̲a̲l̲s̲

             The remote terminals at CRT A and CRT B will be
             tested against the main site equipment.



         17  T̲e̲s̲t̲ ̲o̲f̲ ̲R̲e̲m̲o̲t̲e̲ ̲T̲A̲R̲E̲ ̲S̲i̲t̲e̲s̲ ̲A̲ ̲a̲n̲d̲ ̲B̲

             The remote TARE connections will be tested by using
             loop back plugs.

         18  I̲n̲v̲e̲n̲t̲o̲r̲y̲ ̲C̲h̲e̲c̲k̲

             The CR installation team will conduct an inventory
             check of all delivered CAMPS equipment, including
             documents, test equipment and spare parts.

             This inventory check will be witnessed by the customer
             and is part of the SPA.

         19  C̲O̲M̲S̲E̲C̲ ̲T̲e̲s̲t̲

             The CR installation team will run the system for
             the one day test in the CAMPS room.

             COMSEC radiation survey personal will be trained
             in running the user terminals for further COMSEC
             test of these terminals after the SPA test.

         20  S̲i̲t̲e̲ ̲P̲r̲o̲v̲i̲s̲i̲o̲n̲a̲l̲ ̲A̲c̲c̲e̲p̲t̲a̲n̲c̲e̲ ̲(̲S̲P̲A̲)̲

             Site provisional acceptance is the act whereby
             SHAPE will acknowledge by protocol that CR has
             fully demonstrated that a site is complete and
             ready for initial operation and will take place
             when the following requirements have been met:

             1)  Completion of an agreed on-site acceptance
                 test.

             2)  Completion of the site inventory list and the
                 mutually agreed discrepancy list showing the
                 agreed date for clearance of each listed discrepancy.

         21  P̲a̲c̲k̲i̲n̲g̲

         22  T̲r̲a̲v̲e̲l̲t̲i̲m̲e̲ ̲t̲o̲ ̲N̲e̲x̲t̲ ̲S̲i̲t̲e̲