⟦e54ebb4ca⟧ Wang Wps File

    Length: 12360 (0x3048)
    Types: Wang Wps File
    Notes: CPS/TCN/071               
    Names: »3786A «

Derivation

└─⟦011bcd343⟧ Bits:30006160 8" Wang WCS floppy, CR 0242A
    └─ ⟦this⟧ »3786A « 

WangText



       3786A/rt
…02…CPS/TCN/071

…02…HAU/830826…02……02…#
CAMPS SITE PROVISIONAL ACCEPTANCE
SITE 2-16…02……02…CAMPS








…0f…




                 CAMPS SITE PROVISIONAL ACCEPTANCE 
                 SITE 2-16 Manual
                                              

                 CPS/TCN/071
                                          
                                  









         

         

                 Hans Erik Haureberg 




                 Kurt Nybroe-Nielsen






                 SHAPE (1), BHB, KNN, CL, LU, URH,
                 Conf. Mgmt., QA, PMS, KM, Library (5)  
                 GQAR














                          Install. Mgr.  830826


         Issue 2    



         830826
…0e…                          Conf.Mgmt.     830826



    3786A/rt       …02…CPS/TCN/071

 …02…HAU/830826…02……02…ii
CAMPS SITE PROVISIONAL ACCEPTANCE          
SITE 2 - 16       …02……02… CAMPS












      830517                  All                         
   1  830826                  All      Update according to
                                     Camps log no. 1338



   3786A/rt       …02… CPS/TCN/071

                                            …02…HAU/830826…02……02…iii
CAMPS SITE PROVISIONAL ACCEPTANCE          
SITE 2 - 16       …02……02… CAMPS





                                      T̲A̲B̲L̲E̲ ̲O̲F̲ ̲C̲O̲N̲T̲E̲N̲T̲S̲




     1.  GENERAL ....................................  
         1 
       1.1   PURPOSE ................................  
             1 
       1.2   APPLICLABLE DOCUMENTS ..................  
             1 
       1.3   TERMS AND ABBREVIATIONS ................  
             2 

     2   INVENTORY CHECK ............................  
         3 
       2.1   PURPOSE ................................  
             3 
       2.2   SCHEDULE ...............................  
             3 

     3   ECO STATUS CHECK ...........................  
         4 
       3.1   PURPOSE ................................  
             4 
       3.2   PERSONNEL REQUIREMENTS .................  
             4 
       3.3   CONFIGURATION LIST .....................  
             4 
       3.4   OFFICIAL ECO STATUS CHECK ..............  
             5 
       3.5   SCHEDULE ...............................  
             5 

     4   COMSEC ON-SITE VERIFICATION ................  
         6 
       4.1   PURPOSE ................................  
             6 
       4.2   PERSONNEL REQUIREMENTS .................  
             6 
       4.3   HARDWARE REQUIREMENTS ..................  
             6 
       4.4   SOFTWARE REQUIREMENTS ..................  
             6 
       4.5   FUNCTIONAL DESCRIPTION .................  
             6 
       4.6   ACCEPTANCE CRITERIA ....................  
             7 
       4.7   SCHEDULE ...............................  
             7 

     5   ON-SITE SOFTWARE VERIFICATION ..............  
         8 
       5.1   PURPOSE ................................  
             8 
       5.2   PERSONNEL REQUIREMENTS .................  
             8 
       5.3   HARDWARE REQUIREMENTS ..................  
             8 
       5.4   SOFTWARE REQUIREMENTS ..................  
             8 
       5.5   FUNCTIONAL DESCRIPTION .................  
             8 
       5.6   ACCEPTANCE CRITERIA ....................  
             9 
       5.7   SCHEDULE ...............................  
             9 




   3786A/rt       …02… CPS/TCN/071

                                            …02…HAU/830826…02……02…iv
CAMPS SITE PROVISIONAL ACCEPTANCE          
SITE 2 - 16       …02……02… CAMPS






     6   UPDATED AS TO BE BUILT DRAWINGS ............  
         9 
       6.1   AS TO BE BUILT .........................  
             9 
       6.2   AS BUILT ...............................  
             9 

     7   SITE PROVISIONAL ACCEPTANCE PROTOCOL .......  10
         
       7.1   DOCUMENTS ..............................  10
             
       7.2   FORMAL PROCEDURE .......................  10
             


     8   OVERALL SPA SCHEDULE .......................  11
         


                        1̲ ̲ ̲G̲E̲N̲E̲R̲A̲L̲



1.1      P̲U̲R̲P̲O̲S̲E̲

         The Site Provisional Acceptance (SPA) is the act whereby
         SHAPE will acknowledge by protocol that CR has fully
         demonstrated that a Site is complete and ready for
         initial operation.

         The purpose of this document is to identify all procedures
         and inspections to verify that the equipment has been
         correctly installed, that all items have been supplied
         under terms of the contract and that the system is
         able to execute the basic software functions.



1.2      A̲P̲P̲L̲I̲C̲A̲B̲L̲E̲ ̲D̲O̲C̲U̲M̲E̲N̲T̲S̲

         1.  CAMPS SYSTEM REQUIREMENTS SPECIFICATION,
             CPS/210/SYS/001.

         2.  CAMPS SYSTEM DESIGN SPECIFICATION,
             CPS/SDS/001.

         3.  CAMPS DOCUMENTATION PLAN
             CPS/PLN/008

         4.  CAMPS INVENTORY LIST;
             CPS/AUX/0  

         5.  CAMPS HARDWARE ASSEMBLY
             BREAKDOWN/HARDWARE TREE,
             CPS/SDS/017

         6.  CAMPS ACCEPTANCE TEST SPECIFICATION
             OVERVIEW
             CPS/TSS/001.

         7.  CAMPS ACCEPTANCE PLAN
             CPS/PLN/012

         8.  SYSTEM INTEGRATION AND TEST PLAN
             CPS/TSP/005



         9.  CAMPS INVENTORY CHECK PROCEDURE SITE 2-16 CPS/TCN/072

         10. CAMPS SITES 2-16 TEST PROCEDURE

         11. CONFIGURATION REFERENCE LIST FOR CAMPS MODULES
             CPS/TCN/057

         12. LIST OF SUBASSEMBLIES INCLUDES IN PERIPHERALS AND
             EQUIPMENT FOR SITE XX.

         13  SITE ASPL



1.3      T̲E̲R̲M̲S̲ ̲A̲N̲D̲ ̲A̲B̲B̲R̲E̲V̲I̲A̲T̲I̲O̲N̲S̲


         ATBB        As to be built
         CR          Christian Rovsing A/S
         ECO         Engineer Change Order
         CAMPS       Computer Aided Message Progressing System
         COMSEC      Communication Security
         PTP         Paper Tape Puncher
         PTR         Paper Tape Reader
         SHAPE       Supreme Headquarters Allied Powers Europe
         SPA         Site Provisional Acceptance
         VDU         Visual Display Unit
         SRS         System Requirement Specification
         SDS         System Design Specification


                    2̲ ̲ ̲I̲N̲V̲E̲N̲T̲O̲R̲Y̲ ̲C̲H̲E̲C̲K̲



2.1      P̲U̲R̲P̲O̲S̲E̲

         The Inventory Check shall verify that all equipment
         to subassembly level related to the actual site has
         been delivered in accordance with the contents of the
         property inventory list.
         The Inventory Check is to be performed in accordance
         with the inventory check porcedure CPS/TCN/072 (ref.
         9 document).



2.2      S̲C̲H̲E̲D̲U̲L̲E̲

         The duration of the official inventory check is scheduled
         to 2 days and will be performed together with the ECO
         status check.





                   3̲ ̲ ̲E̲C̲O̲ ̲S̲T̲A̲T̲U̲S̲ ̲C̲H̲E̲C̲K̲



3.1      P̲U̲R̲P̲O̲S̲E̲

         The ECO status check shall verify that all delivered
         modules and other units have been delivered in the
         latest baseline ECO version. Using CPS/TCN/057 Configuration
         Reference List.



3.2      P̲E̲R̲S̲O̲N̲N̲E̲L̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲

         The ECO status check will be conducted by CR and witnessed
         by SHAPE representative.



3.3      C̲O̲N̲F̲I̲G̲U̲R̲A̲T̲I̲O̲N̲ ̲L̲I̲S̲T̲

         a)  CR will prepare a configuration list of the site.

         b)  The configuration list includes the following data
             elements:

             1)  Site Number
             2)  Item Number
             3)  CR Type No.
             4)  Description
             5)  CR Part No.
             6)  Serial No.
             7)  ECO Status
             8)  Assembly Reference *)
             9)  Remarks



             *)  The Assembly Reference will be a separate document
                 which contains the following information: CR
                 Part No., Assembly Reference, and a column
                 for Serial Numbers.



3.4      O̲F̲F̲I̲C̲I̲A̲L̲ ̲E̲C̲O̲ ̲S̲T̲A̲T̲U̲S̲ ̲C̲H̲E̲C̲K̲

         a)  CR will perform an official ECO Status Check.

         b)  The configuration list will form the record of
             the ECO Status on all delivered equipment.

         c)  The official ECO Status check will be witnessed
             by the customer.

         d)  The verification part of the configuration list
             will be signed by both parties.



3.5      S̲C̲H̲E̲D̲U̲L̲E̲

         The duration of the ECO Status check is scheduled to
         2 days and will be performed together with the official
         inventory check.

.


              4̲ ̲ ̲C̲O̲M̲S̲E̲C̲ ̲O̲N̲-̲S̲I̲T̲E̲ ̲V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲



4.1      P̲U̲R̲P̲O̲S̲E̲

         This test shall verify that the electro magnetic radiation
         from all installed CAMPS equipment in the CAMPS room
         is in compliance with the requirements described in
         the SRS (Ref. Doc.No. 1) Para 3.5.2.10.



4.2      P̲E̲R̲S̲O̲N̲N̲E̲L̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲

         The test is to be conducted by and under the responsibility
         of the National COMSEC authorities.

         Purchaser will supervise the verification and the CR
         test engineers will assist in operating the system.



4.3      H̲A̲R̲D̲W̲A̲R̲E̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲

         All On-Site installed CAMPS equipment.



4.4      S̲O̲F̲T̲W̲A̲R̲E̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲

         The complete CAMPS Software System.



4.5      F̲U̲N̲C̲T̲I̲O̲N̲A̲L̲ ̲D̲E̲S̲C̲R̲I̲P̲T̲I̲O̲N̲

         Test specification and procedures shall be delivered
         by SHAPE/ACE COMSEC.





4.6      A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲ ̲C̲R̲I̲T̲E̲R̲I̲A̲

         The verification of the equipment compliance with requirements
         stated in the SRS Para 3.5.2.10 will establish the
         acceptance criteria.



4.7      S̲C̲H̲E̲D̲U̲L̲E̲

         The verification shall take place in conjunction with
         the SPA and the duration of the test is scheduled to
         2 days.


             5̲ ̲ ̲O̲N̲-̲S̲I̲T̲E̲ ̲S̲O̲F̲T̲W̲A̲R̲E̲ ̲V̲E̲R̲I̲F̲I̲C̲A̲T̲I̲O̲N̲



5.1      P̲U̲R̲P̲O̲S̲E̲

         a)  The purpose of this test is to give a site related
             verification of the CAMPS functional and operational
             performance.

         b)  Test Procedures and Test Reports for this test
             are submitted by CR and approved by Shape prior
             to SPA.



5.2      P̲E̲R̲S̲O̲N̲N̲E̲L̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲

         The CAMPS System shall be operated by CR test engineers
         and witnessed by SHAPE representatives.



5.3      H̲A̲R̲D̲W̲A̲R̲E̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲

         The Hardware required for conducting the test is the
         all on-site installed CAMPS hardware according to the
         CAMPS hardware assembly breakdown/hardware tree, 
         Ref. Doc. CPS/SDS/017.



5.4      S̲O̲F̲T̲W̲A̲R̲E̲ ̲R̲E̲Q̲U̲I̲R̲E̲M̲E̲N̲T̲S̲

         The Software Package required for conducting this test
         is the complete CAMPS software system.



5.5      F̲U̲N̲C̲T̲I̲O̲N̲A̲L̲ ̲D̲E̲S̲C̲R̲I̲P̲T̲I̲O̲N̲

         The verification of the CAMPS basic functional performance
         is accomplished by conducting an exercise of the functions
         specified in the agreed test procedure.


5.6      A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲ ̲C̲R̲I̲T̲E̲R̲I̲A̲

         The verification of the functional performance in compliance
         with the agreed test procedures shall establish the
         acceptance criteria.



5.7      S̲C̲H̲E̲D̲U̲L̲E̲

         The Test will start immediately after completion of
         the COMSEC on-site verification. The duration of the
         test is scheduled to 5 days.









            6̲ ̲ ̲U̲P̲D̲A̲T̲E̲D̲ ̲A̲S̲-̲T̲O̲-̲B̲E̲-̲B̲U̲I̲L̲T̲ ̲D̲R̲A̲W̲I̲N̲G̲S̲



6.1      A̲S̲-̲T̲O̲-̲B̲E̲-̲B̲U̲I̲L̲T̲

         a)  The As-To-Be-Built drawings (ATBB) will be updated
             by Pen and Ink during the installation period to
             reflect how all the major assemblies of the supplied
             equipment have been installed and integrated at
             the time of the SPA.

         b)  One set of the pen and ink updated ATBB drawings
             will be handed over to the SHAPE representative
             at the time of the SPA.



6.2      A̲S̲ ̲B̲U̲I̲L̲T̲ ̲D̲R̲A̲W̲I̲N̲G̲S̲

         The As Built Drawings will be supplied by CR 6 weeks
         after the SPA as an appendix to the installation manual.


         7̲ ̲ ̲S̲I̲T̲E̲ ̲P̲R̲O̲V̲I̲S̲I̲O̲N̲A̲L̲ ̲A̲C̲C̲E̲P̲T̲A̲N̲C̲E̲ ̲P̲R̲O̲T̲O̲C̲O̲L̲



7.1      D̲O̲C̲U̲M̲E̲N̲T̲S̲

         The SPA Protocol will be submitted by SHAPE.



7.2      F̲O̲R̲M̲A̲L̲ ̲P̲R̲O̲C̲E̲D̲U̲R̲E̲

         Upon completion of the SPA, an SPA acceptance protocol
         will be signed by at least one representative from
         CR and one from SHAPE or SHAPE will deliver to CR in
         writing a "Notice of Defects" listing the defects which
         prevented provisional acceptance of the site.

         The date of signature of the SPA Acceptance Protocol
         marks the date of the SPA.

         If SHAPE delivers a "Notice of Defects" then the date
         on which SHAPE signs a "Correction of Defects Notice"
         shall be the date of the SPA.

         "Defects", as referred to above, means any non-compliance
         with the contract by CR which prevents the normal operation
         of the site. "Discrepancies" shall mean a non-compliance
         which does not prevent completion of site provisional
         acceptance. However, any discrepancies existing at
         the time of signing the Site Provisional Acceptance
         Protocol will be listed in the protocol and dates for
         correction of each will also be included.

         The date of the SPA marks the time at which SHAPE takes
         over the responsibility of a site and the operation
         of the site can commence.


                 8̲ ̲ ̲O̲V̲E̲R̲A̲L̲L̲ ̲S̲P̲A̲ ̲S̲C̲H̲E̲D̲U̲L̲E̲



         The planned time period for the site provisional acceptance
         procedures is scheduled to be 2 weeks as showed in
         the below overall task schedule.





                      DAY:   1   2   3   4   5   6   7   8   9   10 11 12

Official inv.check:
ECO Status Check:
COMSEC Verification:
Software Verificat.
Updated ATBB
ACCEPTANCE Protocol