DataMuseum.dk

Presents historical artifacts from the history of:

CR80 Wang WCS documentation floppies

This is an automatic "excavation" of a thematic subset of
artifacts from Datamuseum.dk's BitArchive.

See our Wiki for more about CR80 Wang WCS documentation floppies

Excavated with: AutoArchaeologist - Free & Open Source Software.


top - download

⟦f06c572ae⟧ Wang Wps File

    Length: 9576 (0x2568)
    Types: Wang Wps File
    Notes: CR Corp. - TDS contract   
    Names: »1488A «

Derivation

└─⟦0c861a53d⟧ Bits:30006079 8" Wang WCS floppy, CR 0122A
    └─ ⟦this⟧ »1488A « 

WangText





                     -  #  -







     1981-12-18       GJ/am]

to.: CR Corp.
   Att.: BRV

Fr.: Christian Rovsing A/S
     Gert Jensen

Our ref.: GJ/am]/LET/0036

Subject: TDS Contract
---------------------

Ref.:    a)          CPS/110/TLX/0018
     b)  CRC/FAX/0065

This fax serves two purposes. First, to continue ref.
 a) explaining why we took the drastic step. Secondly,
 to give you a reply to your fax, ref. b), which we basically
 consider a sad collection of unjustified accusations
 and an uninhibited treatment of the facts.

We trust we can find a more professional level to continue
 our dialog at. We therefore, in the following tell you
 what we consider facts, and which of these facts led
 to the current situation.


Fact 1:  Prior to contract signature (nov. 80) CRC and
         CRAS agreed to a total cost for the TDS and
         LITSYNC contracts of 2.1. Mio. Dkr. devided
         evenly on the two contracts.

Fact 2:  CRC wanted a different payment plan (Jan. 81).
         Instead of deviding the amount evenly, CRC
         wanted 1.2. Mio. on the LITSYNC contract and
         0.9 Mio. on the TDS contract. CRC in this way
         created a less advantageous payment plan for
         themselves on the TDS contract.

Fact 3:  The price for the TDS contract was finalized
         on 22. Jan. 81 to 167,000 dollars. CPS/100/tlx/0075.

Fact 4:  The TDS contract was mutually agreed upon and
         signed on 12. march 81.

         During the final negotiations CR A/S agreed
         to provide extra funding for the TDS effort
         amounting to extra 83,400 US dollars to a total
         of US dollars 250,400.

         CRC at this time received an increase of 50
         percent.



Fact 5:  The contract specified a start date of first
         week in april 81.

Fact 6:  A down payment of 40 percent = 100,160 US dollars
         was paid to CRC to finance the TDS effort up
         to October 81, at which date package A and
         B should have been delivered to CR A/S.

Fact 7:  The 1. July CRC should have delivered to CRAS
         package A and the development plan (contract
         clause 4). Therefore, CRAS asks CRC for the
         status on 18. June 81.

Fact 8:  On 28. June 81 CRC announced the first schedule
         slippage. (THOK/TWX/0223). CRAS is convinced
         that no or very little effort at that time
         has been spent by CRC, which is backed up by
         CRC's info in the TWX/0223 para. 3.

Fact 9:  On 3rd July 81, CPS/100/tlx/0153, we ask CRC
         to produce the development plan per 15. july
         81, with the purpose of getting a complete
         picture of the activities involved (including
         the CRAS activities) and a realistic picture
         of the delivery dates.

Fact 10: At a meeting in CPH 16 - 17 july 81 CRC disclosed
         that E.I would be brought onto the program
         1. aug. 81. Additional info disclosed that
         9 people were needed on the program in order
         to maintain the schedule.

         If CRC continued the program with 5 people
         the program would be completed approx. March
         1983!! CRAS askes CRC to evaluate the situation.
         A new meeting was scheduled for 24. Aug. 81
         at CRC. The intention of the meeting was as
         stated under fact 9. (M.O.M. 15).

Fact 11: On 24. July 1981, CPS/100/tlx/0161, CRAS offered
         their assistance in order to get the program
         off the ground.

Fact 12: On 30. July 1981, CPS/100/tlx/0165, CRAS ask
         you for an answer to our offer of assistance.

Fact 13: On 4. aug. 1981 CRC in telex THOK/TWX/0293,
         turned down the CRAS assistance in form of
         manpower irregardless that this was the most
         scarce resource at CRC!!

         At the same time you informed us of another
         two weeks delay on the start, by telling us
         that E.I would start two weeks later; i.e.
         15. aug. 81.

         Here we are 5 month into the program according
         to the original schedule, and we have not yet
         started.



Fact 14: On 12. august 1981, THOK/TWX/0302, CRC suggests
         that the meeting which CRAS urgently has been
         looking for in order to get enough inside into
         the program, so decision could be made (see
         fact 9, 10), should be moved to a nondisclosed
         date in september.

         Time was running and we were still not getting
         anywhere.

Fact 15: On 18. August 1981, CPS/100/tlx/0175, CRAS
         once again express their concern and suggest
         that the meeting takes place on 7. september
         1981. CRC can have no doubt from the telex
         what CRAS position is by then.

         In THOK/TWX/0322, 27. aug. 81, CRC seems to
         agree with the suggested date.

Fact 16: On 10 sept. 81 CRC was still not able to meet
         with CRAS. Therefore CRAS asks for a new meeting
         date of 21. september 81. See CPS/100/tlx/0190.

Fact 17: On 14. sept. 81 CRC informs CRAS that they
         are unable to meet with us. At the same time
         they announce that HM has left.

         Do I have to tell you where we had the confidence
         to the TDS development effort?

         CRC suggested a new meeting date of 28. sept.
         81.

Fact 18: On 26. sept. 81, THOK/TWX/0375, CRC once again
         moves the meeting to the end of october 81.
         In total the planning meeting has now been
         moved 4 month!! Every time on behalf of CRC.

Fact 19: The time from late september until late october
         was spent working to our satisfaction.

Fact 20: On the 5. nov. 81, CRC/FAX/0052, CRC sends
         us a list of H/W equipment to be delivered
         by CRAS in order to support the TDS development
         offer. The only problem is that this information
         should have been part of the development plan
         due on 1. July 81. See contract para. 5.

Fact 21: On 6. Nov. 1981 CR delivers the package B "User
         Manual and System Design", and CRAS immediately
         begin to review the documents. Also we receive
         the development plan.

         The review/planning meeting is then scheduled
         for the 19 - 20 nov. 81.



Fact 22: On 13. Nov. 81, THOK/TWX/0423 CRC inform CRAS
         that BRV will not be available at the meeting!

         For this reason G. Jensen informs CRC that
         he will not travel to LA.

Fact 23: At the meeting at CRC on 19., 20. and 23. it
         was disclosed that the program definitely was
         in trouble. It would be extremely difficult
         to meet the needs of the CAMPS program schedule.
         However, CRC recognized the problem and expressed
         that more people should be added to the team
         instead of the 2 people working on the program.

Fact 24: In spite of the fact that the contract is a
         fixed price contract and in spite of the fact
         that the program only had been manned with
         2 - 3 people for a short period of time and
         in spite of the fact that the contract value
         was increase by 50 percent on 12. march 81,
         then CRC send CRAS a letter (CRC/LET/0783,
         dated 23. nov. 81) where they express that
         CRAS shall provide additional 100.000 US dollars
         if the program schedule shall be maintained.

         CRAS was more than surprised, but did not respond
         immediately because CRAS did not know how to
         deal with this problem.

Fact 25: On 3rd Dec. 81, THOK/TWX/0441, CRC informs
         CRAS that they will stop the program temporarily!!
         This was a completely unfounded decision which
         nobody around here understood. On the contrary
         we were quite astonished.

         We checked if it was a threat by calling E.I.
         But, sure E.I. was at Hughes.

         Now we find ourselves in a situation where
         CRC - hopelessly behind schedule - after approximately
         5 manmonth of work accuses CRAS of not funding
         the program and furthermore stops the program
         ! ? ! ?
             -------------------------------------

         This situation is so fantastic that nobody
         around here can make sence of it. The only
         conclusion we can come to is that this situation
         has been thorughly planned in advance. We conclude
         this because E.I. went to Hughes no later than
         the day the telex THOK/TWX/0441 was sent.

         Furthermore we conclude that CRC only attempted
         to get the next 25 percent of the contract
         value paid before the people were transferred
         to a different program. We do not believe that
         CRC has any intention of completing the TDS
         program.



         If CRC please look back over this very sad
         story, I hope CRC can see that they created
         a situation, where we had no other choise than
         terminating the contract.

-------------------------------------------------------------------

I now turn to ref. b.

We are very impressed with the energy CRC has shown
 putting this FAX together. Had CRC shown the same energy
 earlier on the program this situation had been avoided.

Your point
2.1  Unsubstantiated. See fact 2, 4, 6, 25.

2.2  Unsubstantiated. See fact 7 - 18.

2.4  Yes, CRC has certainly brought a major program
     into danger.

3.2  Unjustified. CRC is the company performing the
     contract.

3.3  Unjustified. See fact 6.
     Also the contract clearly states that the Product
     Spec. and the Users Manual shall be approved by
     CRAS. See contract para. 11. So the payment plan
     is clear.

3.5  Unjustified. See fact 1 - 25. We are surprised,
     and sad.

3.7  We have not delayed CRC. If CRC look at the contract
     para. 7 and 10 they will see that no date is stated.
     This is on purpose. See contract para. 5, 6th bullet.
     CRC shall specify when the items are needed !!

     You never did that. See fact 20.

3.8  Please clarify.

3.9  Bad irrelevant excuse.

3.10 See our answers to 3.7.


6.       I hope CRC can see that they are off the track
         after they have confronted this fax.

-------------------------------------------------------------------



If CRC has any points they still like to bring forward,
 please let us here from you.


Kind regards,

CHRISTIAN ROVSING A/S

Gert Jensen