top - download
⟦f6395e063⟧ Wang Wps File
Length: 19491 (0x4c23)
Types: Wang Wps File
Notes: PC/HBK/001
Names: »2989A «
Derivation
└─⟦71042c85e⟧ Bits:30006244 8" Wang WCS floppy, CR 0251A
└─ ⟦this⟧ »2989A «
WangText
…02… PC/HBK/001
…02… DL/831128…02……02…#
PROTOCOL CONVERTER
EQUIPMENT HANDBOOK…02… …02… PC
5. I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲
The following step-by-step procedure contains a detailed
instruction set of how to install the CR delivered
equipment for the Protocol Converter.
The major tasks of the installation sequence are:
5.1 UNPACKING
5.2 TRANSPORTATION TO SITE
5.3 MOUNTING OF LEVELLERS
5.4 MOUNTING OF POWER LINE FILTER
5.5 REMOUNTING OF MODULES
5.6 INSTALLATION OF INTERNAL POWER/SIGNAL CABLES
5.7 INSTALLATION OF EXTERNAL POWER/SIGNAL CABLES
AND
MOUNTING OF FITTINGS
5.8 INSTALLATION OF MAINTENANCE VDU
5.9 INSTALLATION OF OFF-LINE PU
5.10 INVENTORY CHECK
5.1 U̲N̲P̲A̲C̲K̲I̲N̲G̲
a) The EMI shielded rack for the Protocol Converter
is packed in its original wooden container.
The rack should remain packed during site internal
transportation and only be unpacked close to the
installation site, but if the space along the access
route is limited, the rack can be unpacked before
transportation to the installation site. The racks
is unpacked as follows:
b) Remove the top cover of the wooden container by
demounting the 3 ea 1/4 x 2.1/2" bolts on each
side of the continer and the 4 ea 1/2 - 13 x 2"
bolts, one in each top corner (see Figure 5.1-1).
c) The 4 walls of the container are removed by loosening
the 21 ea 1/4 x 2.1/2" bolts on each short side.
d) The rack is bolted to the container bottom in each
corner by a 1/2 - 13 x 2.1/2" bolt.
e) These bolts are removed from the bottom of the
container.
Figure 5.1-1
RACK CONTAINER
5.2 T̲R̲A̲N̲S̲P̲O̲R̲T̲A̲T̲I̲O̲N̲ ̲T̲O̲ ̲I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲S̲I̲T̲E̲
a) After unpacking, the front and rear door of the
rack must be removed. Check that the serial number
in the rack correspond to the serial number of
the doors.
b) Be carefull not to damage the gaskets on the door.
c) Depending on means of transportation, 4 eyelets
can be mounted in the top of the rack in the position
of the removed 4 ea 1/2 - 13 x 2" bolts.
5.3 M̲O̲U̲N̲T̲I̲N̲G̲ ̲O̲F̲ ̲L̲E̲V̲E̲L̲L̲E̲R̲S̲
a) The 4 levellers are mounted underneath the racks
two by two, by tilting the racks (see ref.z, drawing
1-180).
b) The levellers are mounted to make a distance of
40 mm between the bottom of the rack and the floor.
c) The levellers must be adjusted to ensure equal
distribution of weight on the floor.
5.4 M̲O̲U̲N̲T̲I̲N̲G̲ ̲O̲F̲ ̲P̲O̲W̲E̲R̲ ̲L̲I̲N̲E̲ ̲F̲I̲L̲T̲E̲R̲
a) Place the power line filter (PLF) over the two
front/bottom knockouts in the rack (see ref.z,
drawing 1-180).
The 2.1/2" male adaptor, welded to the PLF is to
be inserted through the right hand knockout seen
from the front.
b) Mount the tightening washer from outside the EMI
shielded rack.
c) Insert the 2.1/2" to 1" reducing bushing and the
outer washer through the left hand knockout into
the PLF (see ref. z, drawing 1-180).
d) Mount the 1" to 3/4" reducing bushing and the 3/4"
45…0e…o…0f… fitting into the 2.1/2" to 1" reducing bushing.
It is very important to the shielding efficiency, that
the fittings are extremely tightened.
5.5 R̲E̲M̲O̲U̲N̲T̲I̲N̲G̲ ̲O̲F̲ ̲M̲O̲D̲U̲L̲E̲S̲
a) For correct physical positioning of the separately
packed modules, refer to the packing list. The
packing list states the serial no. of the unit,
the crate assy no., the slot no. in the crate and
the address of the physical position in the system.
b) The modules are slided into the print guide and
when the edge connector of the print has entered
the connector of the motherboard, the modules are
fastened by the two fixing screws on the front
of the modules.
5.6 I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲I̲N̲T̲E̲R̲N̲A̲L̲ ̲P̲O̲W̲E̲R̲/̲S̲I̲G̲N̲A̲L̲ ̲C̲A̲B̲L̲E̲S̲
All internal signal and power cables are mounted upon
receipt except for the following cables:
a) Due to the removal of all the adapter modules,
the following internal signal cables must be reconnected:
W12 to CSA 1A1A1A15, J1
W13 to CSA 1A1A4A15, J1
W15 to LIA-N 1A1A1A13, J2
W17 to LIA-N 1A1A1A14, J2
W19 to LIA-N 1A1A4A13, J2
W21 to LIA-N 1A1A4A14, J2
b) Power cable W1 is to be connected to the PLF J1.
c) W23 to V28 L/L 1A1A6A14
W24 to V28 L/L 1A1A6A13
W25 to V28 L/L 1A1A6A12
W26 to V28 L/L 1A1A6A11
5.7 I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲E̲X̲T̲E̲R̲N̲A̲L̲ ̲P̲O̲W̲E̲R̲ ̲A̲N̲D̲ ̲S̲I̲G̲N̲A̲L̲ ̲C̲A̲B̲L̲E̲S̲,
A̲N̲D̲ ̲M̲O̲U̲N̲T̲I̲N̲G̲ ̲O̲F̲ ̲F̲I̲T̲T̲I̲N̲G̲S̲
5.7.1 R̲e̲a̲r̲/̲B̲o̲t̲t̲o̲m̲/̲L̲e̲f̲t̲ ̲H̲a̲n̲d̲ ̲P̲e̲n̲e̲t̲r̲a̲t̲i̲o̲n̲
a) Place the tightening washer on the 2.1/2" to 1.1/2"
reducing bushing.
b) Insert the reducing bushing from the outside through
the knock out into the filterbox and tighten it
from the inside by the inner nut (see ref. z, drawing
1-180).
c) Mount the 1.1/2" steel tube in the reducing bushing.
d) Mount the 48 mm metallic conduit to the steel
tube and tighten it by the clamps.
c) Mount the 1.1/2" steel tube by means of the two
nuts to the cable duct and connect the metallic
conduit by clamps (see ref. z, drawing 1-180).
5.7.2 A̲u̲x̲.̲ ̲C̲o̲n̲n̲e̲c̲t̲i̲o̲n̲s̲
a) The aux. connections W731 and W1502 - W1507 are
pulled through the conduct of the left hand filterbox
penetration.
b) The aux. cables are terminated with D25 connector
and mounted inside the filterbox according to ref.
z, drawing 1-181.
For pin assignment, see ref. z.
5.7.3 R̲e̲a̲r̲/̲B̲o̲t̲t̲o̲m̲/̲R̲i̲g̲h̲t̲ ̲H̲a̲n̲d̲ ̲P̲e̲n̲e̲t̲r̲a̲t̲i̲o̲n̲
a) Mount the outer nut on the 2 1/2" to 3/4" reducing
bushing (see ref. z, drawing 1-180).
b) Insert the reducing bushing from the outside into
the filterbox and tighten it from the inside by
the inner nut.
c) Mount the 3/4" 90…0e…o…0f… fitting in the reducing bushing
below the rack.
d) Mount the 3/4" metallic conduit into the 3/4" 90…0e…o…0f…
fitting.
e) The outer end of the conduit is mounted to the
trolley.
5.7.4 O̲P̲T̲O̲ ̲C̲a̲b̲l̲e̲ ̲f̲r̲o̲m̲ ̲T̲h̲e̲ ̲M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲V̲D̲U̲
a) The OPTO cable is pulled through the metallic conduit
for physical protection between the rack and the
maintenance VDU.
b) The OPTO cable passes through the filterbox into
the rack, and out to the front side of the adapter
crate through the cable channel assembly.
c) The OPTO cable will be terminated with special
OPTO connectors and connected to the OPTO module
on the front side of the adapter crate. (See ref.
z, drawing 1-181).
5.7.5 M̲e̲t̲a̲l̲l̲i̲c̲ ̲C̲a̲b̲l̲e̲ ̲f̲r̲o̲m̲ ̲T̲h̲e̲ ̲O̲f̲f̲-̲L̲i̲n̲e̲ ̲P̲U̲
a) The metallic cable between the PC rack and the
off-line PU is run in the metallic conduit together
with the OPTO cable.
b) The cable passes through the filterbox section
wall. See ref. z, drawing 1-181.
c) The cable will be terminated by a D25 connector
and mounted on a filter according to ref. z, drawing
1-181.
5.7.6 F̲r̲o̲n̲t̲/̲T̲o̲p̲/̲R̲i̲g̲h̲t̲ ̲H̲a̲n̲d̲ ̲P̲e̲n̲e̲t̲r̲a̲t̲i̲o̲n̲
C̲A̲U̲T̲I̲O̲N̲: Before terminating the external power
cable, assure that the circuit breaker
in the CAMPS PDB is disconnected or
in condition OFF.
a) Mount the 3/4" 45…0e…o…0f… fitting in the J-box according
to ref. z, drawing 1-180.
b) Connect the 3/4" metallic conduit between the J-box
and the power line filter.
c) The external 220V cable coming from the CAMPS PDB
and the seperate insulated ground wire are pulled
through the conduit into the power line filter.
d) Remove the metallic cover, for access to the PLF,
fastened by 4 screws during transportation. Remaining
26 screws are shipped attached to inside wall of
PLF. The cables and the ground wire are dismantled
and terminated with cable shoes. For details of
the connection to the terminal board see ref. z,
drawing 1-180.
e) Measure with an ohm-meter that no short circuit
exists between the equipment frame ground (cabinet)
and the power line in the PLF.
f) When the cables have been properly connected, the
metallic lid of the PLF is reinstalled, fixed by
the 30 screws.
5.8 I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲T̲H̲E̲ ̲M̲A̲I̲N̲T̲E̲N̲A̲N̲C̲E̲ ̲V̲D̲U̲
The maintenance VDU is to be installed on the upper
shelf of the host nation provided trolley.
5.8.1 P̲o̲w̲e̲r̲ ̲P̲l̲u̲g̲ ̲C̲o̲n̲n̲e̲c̲t̲i̲o̲n̲s̲
Power plug connections must be exchanged to fit host
nation provided power outlets.
P̲O̲W̲E̲R̲ ̲C̲O̲R̲D̲ ̲F̲R̲O̲M̲ ̲D̲E̲L̲T̲A̲ 3̲-̲P̲I̲N̲N̲E̲D̲ ̲P̲L̲U̲G̲
Brown Phase
Blue Neutral
Green/Yellow Ground
5.8.2 T̲e̲r̲m̲i̲n̲a̲t̲i̲o̲n̲ ̲o̲f̲ ̲O̲P̲T̲O̲ ̲C̲a̲b̲l̲e̲s̲
a) To get access to the OPTO T/R located inside the
VDU, unlock the two snappers on the rear and lift
the terminal access cover of the VDU.
b) The OPTO cable is to be pulled through the rear
waveguide (port 3) into the VDU, see ref. z, drawing
1-182.
c) The two fibres will be terminated with special
OPTO connectors.
d) The white fibre must be connected to the transmitter
jack ("out") and the black fibre to the receiver
jack ("in") (see ref. z., drawing 1-182).
e) The OPTO cable will be permanently marked with
cable no. during the termination procedure.
5.8.3 M̲o̲u̲n̲t̲i̲n̲g̲ ̲o̲f̲ ̲K̲e̲y̲b̲o̲a̲r̲d̲ ̲a̲n̲d̲ ̲K̲e̲y̲s̲
a) The keyboard cable is connected to the female D25
connector located on the (front view) lower right
hand front of the terminal. The connector is secured
by the two front screws.
b) Remove the two keys placed on the inside of the
terminal access cover and insert the keys in the
key-lock on front of the terminal.
5.9 I̲N̲S̲T̲A̲L̲L̲A̲T̲I̲O̲N̲ ̲O̲F̲ ̲T̲H̲E̲ ̲O̲F̲F̲-̲L̲I̲N̲E̲ ̲P̲U̲
a) The off-line PU is to be placed on the lower shelf
of the host nation provided trolley (see ref. z,
drawing 1-179).
b) The metallic interface cable W 1508 is to be run
in the 3/4" metallic conduit together with the
OPTO cable for the maintenance VDU.
c) The interface cable is to be terminated by a D25
connector. For pin assignment, see ref. z.
d) The interface cable is to be connected to the CPU-SCM
adapter on the rear side of the off-line PU (see
ref. z, drawing 1-182).
e) The power cable is connected to the switched power
outlet.
5.10 I̲N̲V̲E̲N̲T̲O̲R̲Y̲ ̲C̲H̲E̲C̲K̲
a) As a final step of the installation, the CR installation
team will conduct an inventory check of the delivered
Protocol Converter equipment to verify that the
equipment is complete.
b) The inventory check is performed in accordance
with the updated inventory list prepared by CR.
6. O̲P̲E̲R̲A̲T̲I̲N̲G̲ ̲I̲N̲S̲T̲R̲U̲C̲T̲I̲O̲N̲S̲
6.1 P̲O̲W̲E̲R̲ ̲U̲P̲ ̲A̲N̲D̲ ̲C̲H̲E̲C̲K̲ ̲O̲U̲T̲
6.1.1 P̲C̲ ̲R̲a̲c̲k̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲
1) T̲u̲r̲n̲ ̲o̲n̲: The circuit breaker in the CAMPS
PDB.
C̲h̲e̲c̲k̲: Fuse not blown due to short circuit
in the installation.
2) T̲u̲r̲n̲ ̲o̲n̲: Right hand mains switch in the front/bottom
of the rack.
C̲h̲e̲c̲k̲: Green "power-on" lamp on the mains
switch is lit.
3) T̲u̲r̲n̲ ̲o̲n̲: The two S-fans from the rear side
of the rack.
C̲h̲e̲c̲k̲: Fans to be running.
4) T̲u̲r̲n̲ ̲o̲n̲: Adapter power supply on the rear
side of the adapter crate.
C̲h̲e̲c̲k̲: Green power lamps on the V28 L/L
adapters and OPTO T/R to be lit.
5) T̲u̲r̲n̲ ̲o̲n̲: Power supply of PU 1 (rear side of
PU).
C̲h̲e̲c̲k̲: Blowers inside minicrate to be running.
"Power-on" lamp above power switch
to be lit.
Power lamps on modules to be lit.
6) T̲u̲r̲n̲ ̲o̲n̲: Power supply of PU 2 (rear side of
PU).
C̲h̲e̲c̲k̲: Blowers inside minicrate to be running.
"Power-on" lamp above power switch
to be lit.
Power lamps on modules to be lit.
6.1.2 M̲A̲I̲N̲T̲E̲N̲A̲N̲C̲E̲ ̲V̲D̲U̲
a) Connect the power plug to the wall outlet.
b) Turn on the "power on/off" switch located on the
lower right front of the terminal.
c) Operate the keylock switch to the ON position (turn
right) (right hand front panel).
d) Immediately after power up the terminal executes
a series of system diagnostics. If all are working
properly, a blank screen will be displayed within
10 seconds.
e) Adjust the intensity and focus until the characters
are clear and bright. Do not advance the intensity
too far or the display area may be highlighted.
f) Adjust the audible alarm for the desired sound
level (control shift and the G key).
6.2 S̲y̲s̲t̲e̲m̲ ̲I̲n̲i̲t̲i̲a̲l̲i̲z̲a̲t̲i̲o̲n̲
As a result of a "power up" or a "Master Clear" button
activation the PC enters the Maintenance Mode.
The system will at any time be in one of four modes,
each mode defining a state with certain capabilities.
The system modes are:
a) Maintenance Mode
b) Local Mode
c) Operational Mode
d) Test Mode
The system is controlled by an operator who - via the
maintenance VDU - communicates with the system giving
commands and receiving responses. The execution of
a command may change the current mode of the system
and the current mode defines which commands are accepted.
The system will display a prompt on the VDU when ready
to receive a command. This prompt will also show the
current mode of the system.
Once the system is brought into operational mode, the
VDU may be dis-patched from the converter which will
continue operating unaffected.
The relationship between modes and commands is depicted
in Figure 6.2-1 and further described in ref.u.
POWER UP
MASTER CLEAR
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
MAINTENANCE
MODE
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲C̲H̲E̲C̲K̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲D̲U̲M̲P̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲I̲N̲I̲T̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
LOCAL…01…MODE
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲L̲O̲G̲O̲N̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
OPERATIONAL
MODE
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲S̲H̲O̲W̲ ̲S̲T̲A̲T̲I̲S̲T̲I̲C̲S̲ ̲ ̲ ̲
̲ ̲ ̲R̲E̲S̲E̲T̲ ̲S̲T̲A̲T̲I̲S̲T̲I̲C̲S̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲L̲O̲G̲O̲F̲F̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲T̲E̲S̲T̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
TEST
MODE
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲S̲H̲O̲W̲ ̲S̲T̲A̲T̲I̲S̲T̲I̲C̲S̲ ̲ ̲ ̲
̲ ̲ ̲R̲E̲S̲E̲T̲ ̲S̲T̲A̲T̲I̲S̲T̲I̲C̲S̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲V̲E̲R̲I̲F̲Y̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲L̲O̲G̲O̲F̲F̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
Figure 6.2-1
Command-Induced Mode-Transistions
6.3 S̲T̲A̲T̲U̲S̲ ̲D̲I̲S̲P̲L̲A̲Y̲S̲
6.3.1 C̲P̲U̲-̲S̲C̲M̲ ̲I̲n̲d̲i̲c̲a̲t̲o̲r̲s̲
Two LED's on the front panel are marked "POWER" (green)
and "TEST" (red). The functions of these two LED's
are specified as follows:
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲
POWER TEST DESCRIPTION
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲
0 0 Power off, or not valid
0 1 Power not valid after power failure
1 0 Power valid
1 1 Power valid after power failure
̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲ ̲
̲ ̲ ̲ ̲ ̲ ̲ ̲
6.3.2 R̲A̲M̲ ̲a̲n̲d̲ ̲E̲P̲R̲O̲M̲ ̲I̲n̲d̲i̲c̲a̲t̲o̲r̲s̲
On each module front panel, a green LED marked "POWER"
indicates that the primary power is applied to the
module and that the power regulators are operating
satisfactorily.
6.3.3 L̲T̲U̲ ̲I̲n̲d̲i̲c̲a̲t̲o̲r̲s̲
3 LED's are mounted on the front panel:
POWER: green Indicates when +12, -12
and +5 power supply is
present at the module.
BOOTL: yellow Indicates when the LTU
is in Bootload Mode.
TEST: red If the selftest of the
LTU has succeeded, the
LED is turned off. If
failure, the LED is flashing.
6.3.4 O̲P̲T̲O̲ ̲T̲/̲R̲ ̲I̲n̲d̲i̲c̲a̲t̲o̲r̲s̲
The OM-1 and OM-2 have the same status display functions.
Five LED lamps provide a continuous indication on the
status of the OPTO T/R.
PWR: This green indicator should be on continuously.
It indicates that primary power is applied to the OPTO
T/R and that the power regulators are operating satisfactorily.
RCVL: This red indicator should be off during normal
operation. When this LED is on it indicates that the
amplitude of the receive signal is within 3 dB of the
minimum acceptable level; or that the frequency of
the received signal is not correct.
RTS: This yellow indicator will be on whenever the
Request to Send input is present from the associated
device.
CTS: This yellow indicator will be on whenever a Clear
to Send output is applied to the associated device.
SYNC: This red indicator should be off during normal
operation. When this LED is on it indicates that the
OPTO T/R is attempting to establish synchronization.
6.3.5 V̲.̲2̲8̲ ̲L̲/̲L̲ ̲A̲d̲a̲p̲t̲e̲r̲ ̲I̲n̲d̲i̲c̲a̲t̲o̲r̲s̲
The only status lamp on the V.28 L/L Adapter is the
green power-on indicator.
An ON condition indicates that the primary power is
applied to the adapter and that the power regulators
are operating satisfactorily.
6.3.6 V̲D̲U̲ ̲S̲t̲a̲t̲u̲s̲ ̲I̲n̲d̲i̲c̲a̲t̲i̲o̲n̲
a) Upon power-up, the power-up diagnostic test (flickering
pictures) determines the amount of RANDOM ACCESS
MEMORY (RAM) installed, and executes a diagnostic
test to check RAM. EPROM is also checked and checksums
are then computed and compared against the value
stored in the ERASABLE PROGRAMMABLE READ ONLY MEMORY
(EPROM) at locations FFEC-FFFBH.
If a RAM memory error is found, the following message
is displayed:
MEM ERR: ADR XXXX YY
ZZ
where XXXX is the hexadecimal address.
YY is the contents of that address.
ZZ is the expected value.
If the EPROM checksums are incorrect, the message:
BAD EPROM CHECKSUM xxxx xxxx
....
(where xxxx= addresses of the bad EPROMS)
is displayed along with the DIAGNOSTIC menu.
If the RAM and EPROM checksums are good a clear
screen will occur with the words TTY RESET above
the status line.
b) For use of Diagnostic Menu and other diagnostic
and status function refer to the VDU Technical
Manual
(ref. p.).
7. M̲A̲I̲N̲T̲E̲N̲A̲N̲C̲E̲
7.1 P̲r̲o̲t̲o̲c̲o̲l̲ ̲C̲o̲n̲v̲e̲r̲t̲e̲r̲ ̲L̲e̲v̲e̲l̲
Maintenance of the Protocol Converter will be initiated
from the CAMPS main site by the Resident Site Technician
and the Maintenance Technician.
7.2 M̲A̲I̲N̲T̲E̲N̲A̲N̲C̲E̲ ̲M̲A̲N̲U̲A̲L̲ ̲(̲R̲e̲f̲.̲ ̲u̲.̲)̲
The maintenance manual is divided into 7 sections,
each covering a well defined part of the Protocol Converter
equipment site maintenance. The contents of the major
sections is shortly described below:
7.2.1 T̲h̲e̲ ̲P̲r̲e̲v̲e̲n̲t̲i̲v̲e̲ ̲M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲(̲R̲e̲f̲.̲ ̲u̲.̲ ̲S̲e̲c̲.̲ ̲3̲)̲
Describes the scheduled preventive maintenance to be
carried out on the rack and the peripheral equipment.
7.2.2 T̲h̲e̲ ̲C̲o̲r̲r̲e̲c̲t̲i̲v̲e̲ ̲M̲a̲i̲n̲t̲e̲n̲a̲n̲c̲e̲ ̲(̲R̲e̲f̲.̲ ̲u̲.̲ ̲S̲e̲c̲.̲ ̲4̲)̲
The objective of the corrective maintenance is to detect
whenever an error is occurring, perform the repair
necessary, and bring the system back to normal operation.
This is achieved by using the structured troubleshooting
procedures.
Ref. u. contains the troubleshooting procedures in
which the strategy of tracing a detected error is described.
When the error is isolated to a particular module,
this is interchanged with a spare module. A verification
test is performed before reloading the application
programs and bringing the system back to normal operation.
7.2.3 T̲h̲e̲ ̲F̲a̲i̲l̲u̲r̲e̲ ̲R̲e̲p̲o̲r̲t̲i̲n̲g̲ ̲S̲y̲s̲t̲e̲m̲ ̲(̲R̲e̲f̲.̲ ̲u̲.̲ ̲S̲e̲c̲.̲ ̲6̲)̲
Contains a description of the paperwork at site level.
7.2.4 T̲h̲e̲ ̲T̲o̲o̲l̲s̲ ̲a̲n̲d̲ ̲T̲e̲s̲t̲ ̲E̲q̲u̲i̲p̲m̲e̲n̲t̲ ̲(̲R̲e̲f̲.̲ ̲u̲.̲ ̲S̲e̲c̲.̲ ̲7̲)̲
Lists the tools and test equipment required for site
maintenance.