⟦fc6c02912⟧ Wang Wps File

    Length: 9340 (0x247c)
    Types: Wang Wps File
    Notes: SYS INTERN MEDDELELSE 137 
    Names: »4534A «

Derivation

└─⟦61f87be83⟧ Bits:30006024 8" Wang WCS floppy, CR 0420A
    └─ ⟦this⟧ »4534A « 

WangText

…00……00……00……00……00……86…1                                             …02…           …02…   …02…        

…02…

…02…RH/840126…02……02…#
INTERN MEDDELELSE NR. 137
…02……02…SYS.DIV.








         To:         GJ, SAR, BRW, OB, OWE, FE, ALF, HAN, HKW,
                     Carol Feil, KM, ORP, PMS

         Fm:         RH


         Subject:    Pollution Control Equipment, PCE, for U.S.
                     Navy Fuel Depot, San Diego
         --------------------------------------------------------


         We have received a draft RFP for the project. It is
         expected that the official RFP will be sent out 29.
         Feb. 84, with a closing date 6 weeks later, e.g. 11th
         April.

         The project is a process control system with message
         generation, inventory control and communication. The
         project covers also uninterruptable power system, Instrumentation
         to fuel tanks, valves as well as installation, documentation,
         and training.

         The US Navy wants a total systems solution. Therefore,
         we have to merge the PROCOS of CRI, the overall system
         solutions of Systems Divisions with the contacts and
         knowledge of the US offices.

         Attached is the first proposal plan, and revision will
         come as the requirements emerge. Please provide all
         comments as early as possible.



         Ralf Hansen





         Attachments:

         1.  Schedule

         2.  Overview tables

             2.1 Product delivery
             2.2 Proposal input
             2.3 Proposal responsibility

         3.  Assignment of responsibility

         4.  Deadlines, phase 1





















































                         SCHEDULE


               T̲A̲B̲L̲E̲ ̲2̲.̲1̲ ̲ ̲P̲R̲O̲D̲U̲C̲T̲ ̲D̲E̲L̲I̲V̲E̲R̲Y̲

         The table provides a summarized list of expected contract
         deliverables against the main suppliers.


                                                    
                CRI  CR-SD CR-  INSTRU-   EXTERNAL  INSTALLATION  ILS/
                                                                  
                                                                 
                           CORP MENT ENG. SUPPLIERS CONTRACTOR    RCA
                ---------------------------------------------------------
Standard Procos  X

Procos Extensions       X

Telecom                X

PAM                                           X

Instruments                                   X

Valves                                        X

UPS                                           X

Housing                                       X

Ducts                                                    X

Installation

- Main Eq.                                                         X
- Instruments                                            X
- Valves                                                 X
- UPS                                                    X

Training

- Maint.                                                           X
- Operators      X

Documentation

- Procos         X                                                 (X)
- Ext. Procos    X                                                 (X)
- Communication        X                                           (X)
- Instruments                                 X                    (X)
- Valves                                      X                    (X)
- UPS                                         X                    (X)

Project Management          X

Configuration
Management       X                                                 (X)


(X) Supplement and coordinate



                    T̲A̲B̲L̲E̲ ̲2̲.̲2̲ ̲ ̲P̲R̲O̲P̲O̲S̲A̲L̲ ̲I̲N̲P̲U̲T̲


                 The table shows the main sources of information for
                 the individual components of the proposal.


                                                    
                CRI  CR-SD CR-  INSTRU-   EXTERNAL  INSTALLATION  ILS/
                                                                  
                                                                 
                           CORP MENT ENG. SUPPLIERS CONTRACTOR    RCA
                ---------------------------------------------------------
Standard Procos  X

Procos Extensions      X

Telecom                X

PAM                    X

Instruments                         X         X

Valves                              X         X

UPS                         X       X         X

Housing          X     X    X       X         X          X         X

Ducts                               X                    X

Installation

- Main Eq.       X                                       X
- Instruments                       X         X          X
- Valves                            X         X          X
- UPS                       X                 X          X

Training

- Maint          X                                                 X
- Operators      X                                                 X

Documentation

- Procos         X                                                 X
- Ext. Procos    X                                                 X
- Communication        X
- Instruments                       X         X                    (X)
- Valves                            X         X                    (X)
- UPS                                         X                    (X)

Project Management          X       X

Configuration
Management       X                  X                    X         X


(X) Supplement and coordinate



         T̲A̲B̲L̲E̲ ̲2̲.̲3̲ ̲ ̲S̲U̲M̲M̲A̲R̲Y̲ ̲O̲F̲ ̲P̲R̲O̲P̲O̲S̲A̲L̲ ̲R̲E̲S̲P̲O̲N̲S̲I̲B̲I̲L̲I̲T̲I̲E̲S̲

                 
                 For details of the tasks, see part 3.


                                                    
                CRI  CR-SD CR-  INSTRU-   EXTERNAL  INSTALLATION  ILS/
                                                                  
                                                                 
                           CORP MENT ENG. SUPPLIERS CONTRACTOR    RCA
                ---------------------------------------------------------
Standard Procos  X

Procos Extensions      X

Telecom                X

PAM                    X

Instruments                         X         

Valves                              X         

UPS                         X                  

Housing                     X                                      
                                                                   

Ducts                               X                     

Installation

- Main Eq.                                                         X
- Instruments                       X         
- Valves                            X         
- UPS                                                              X

Training

- Maint                                                            X
- Operators      X                                                 X

Documentation

- Procos         X
- Ext. Procos    X
- Communication        X
- Instruments                       X
- Valves                            X
- UPS                       X

Project Management          X        

Configuration
Management                                                         X


(X) Supplement and coordinate



             3̲ ̲ ̲A̲S̲S̲I̲G̲N̲M̲E̲N̲T̲ ̲O̲F̲ ̲R̲E̲S̲P̲O̲N̲S̲I̲B̲I̲L̲I̲T̲Y̲



         O̲l̲e̲ ̲B̲u̲k̲,̲ ̲C̲R̲I̲

         Procos to PIU/Instrument interface
         Instrumentation Engineer identification, evaluation
         Instrumentation judgement
         Procos expansion strategy
         Procos expansion description/definition
         Procos options (touchmask, keyboard, graphic display
         - high resolution)
         Procos Power Requirement
         Procos Environmental Requirements
         Procos Documentation
         Procos Training - Maintenance
                Training - Operator
         Maintenance Policy inputs
         Identify potential Instrument suppliers prior to 
           Instrumentation Engineer
         Procos part of Proposal
         Procos Cost
         PAM system interface, if any


         B̲]̲r̲g̲e̲ ̲R̲i̲i̲s̲ ̲V̲e̲s̲t̲e̲r̲g̲>̲r̲d̲,̲ ̲C̲R̲ ̲C̲O̲R̲P̲

         Contractor selection and cost
         Instrumentation engineer identification


         H̲a̲r̲o̲l̲d̲ ̲K̲.̲ ̲W̲i̲l̲s̲o̲n̲ ̲C̲R̲ ̲A̲d̲v̲.̲ ̲S̲y̲s̲

         Identify potential Instrument Suppliers prior to 
           Instrumentation Engineer.
         Provide Naval screening of Proposal
         Provide answers to questions in Proposal




         C̲a̲r̲o̲l̲ ̲F̲e̲i̲l̲,̲ ̲C̲R̲ ̲C̲o̲r̲p̲

         Contractor identification (San Diego area)
         Instrumentation Engineer identification
         Identify applicable standards
         Identify potential problems
         UPS specifications
         Installation feasibility e.g. limitations
         UPS description and cost   
         Housing for electronic equipment


         A̲r̲t̲ ̲F̲r̲i̲e̲d̲m̲a̲n̲,̲ ̲C̲R̲ ̲S̲D̲

         Project management definition
         Project management part of proposal


         K̲u̲r̲t̲ ̲M̲i̲k̲k̲e̲l̲s̲e̲n̲,̲ ̲I̲L̲S̲

         Installation planning coordination
         Develop Installation Specifications (civil works)
         Provide Installation part of proposal (civil works)
         Installation CR80-Procos-Procos expansions in Control
         Room, Fuels Office, NPO (Alexandria, Virginia).


         O̲l̲e̲ ̲R̲e̲n̲e̲ ̲P̲e̲t̲e̲r̲s̲e̲n̲,̲ ̲I̲L̲S̲

         Training planning coordination
         Training - maintenance
         Documentation planning coordination
         Available documentation evaluation

         P̲e̲r̲ ̲S̲]̲n̲d̲e̲r̲g̲>̲r̲d̲,̲ ̲I̲L̲S̲

         Maintenance and Repair policy
         Spares estimate (with CRI)
         Test equipment specs. for proposal
         Repair facilities specs. for proposal



         R̲a̲l̲f̲ ̲H̲a̲n̲s̲e̲n̲,̲ ̲C̲R̲ ̲S̲D̲

         Proposal coordination
         Proposal planning
         PAM system
         Test planning coordination
         Overall system engineering, HW
         Overall system engineering, SW


         N̲i̲e̲l̲s̲ ̲J̲]̲r̲g̲e̲n̲s̲e̲n̲,̲ ̲C̲R̲ ̲S̲D̲

         Telecommunications requirements, cost
         Telecommunications description for proposal
         Telecommunications cost


         G̲e̲r̲t̲ ̲J̲e̲n̲s̲e̲n̲,̲ ̲C̲R̲ ̲S̲D̲

         Proposal judgement
         Proposal evaluation
         Instrumentation Engineer Selection


         I̲n̲s̲t̲r̲u̲m̲e̲n̲t̲a̲t̲i̲o̲n̲ ̲E̲n̲g̲i̲n̲e̲e̲r̲/̲F̲i̲r̲m̲

         Write Instrument specs.
         Write valve specs.
         Identify potential suppliers for Instruments, valves,
         cables
         Write Instrumentation part of proposal
         Write Instrument, valve, installation specs.
         Define Instrument, valve, tests specs.
         Housing analysis RIU, Instruments
         Write ducts specs.



4̲ ̲ ̲D̲E̲A̲D̲L̲I̲N̲E̲ ̲F̲O̲R̲ ̲I̲N̲F̲O̲ ̲A̲N̲D̲ ̲D̲E̲C̲I̲S̲I̲O̲N̲S̲,̲ ̲P̲H̲A̲S̲E̲ ̲1̲,̲ ̲2̲9̲.̲ ̲F̲E̲B̲ ̲1̲9̲8̲4̲

         Medio february, latest:

         Possible proposal support from Instrumentation Engineer/Engineering
         Firm

         At the end of phase 1 the following information and
         decisions shall be available:

         1.  Procos system:

             1.1 UL certification policy and estimated cost

             1.2 Tentative Procos H/W configuration with power
                 consumption

             1.3 Procos expansions for Fuels Office, Communication
                 and NPO, e.g. type of equipment (CR80, CR32).

             1.4 Draft of Procos availability documentation

         2.  Instruments and valves:

             2.1 Potential suppliers of instruments depending
                 on Instrumentation Engineer available.

             2.2 Potential suppliers of valves depending on
                 Instrumentation Engineer available.

             2.3 Specs. of 2.1-2.3 depending on Instrumentation
                 Engineer available.

         3   Power (UPS):

             3.1 Potential suppliers

             3.2 Power system requirements



         4   Installation

             4.1 Potential housing suppliers

             4.2 Potential cable suppliers depending on Instrumentation
                 Engineer available

             4.3 Potential contractors

         5   Maintenance

             5.1 Potential total maintenance suppliers.


         Note:

             Telecom can only be defined, when 1.3 has been
             decided.



         I̲N̲S̲T̲R̲U̲M̲E̲N̲T̲ ̲D̲E̲L̲I̲V̲E̲R̲I̲E̲S̲

         o   Motor operated values: 3

         o   Pipe line tops and isolation values for instrument
             sensors.

         o   Fuel tank level detectors (LIE):  3
             and digital encoders (LT):       34

         o   Tank temperature detection (TE): 80

         o   Fuel tank local thermometer (TI): 15
             (bimetallic or capillary)

         o   Tank high level alarm switch (LSH): 29

         o   Tank bottom sludge and water interface level detector
             (LE): 27

         o   Pressure indicating transmitters (PIT): 43

         o   Pump instrumentation

             -   Pressure switches
             -   Temperature switches
             -   Vibration switches

         o   Motor operators for existing values (MOV*): 6