…02…CPS/MIN/031
…02…BHB/830323…02……02…#
MINUTES OF MEETING NO. 31
…02……02…CAMPS
…0e…TRACOR/CR…0f……02……02… …02……0f…83-03-23…02… 31…02…CR…0e…
Minutes of Meeting on 21st-22nd March 1983
…0f……0f…TRACOR…0e……0e…
Mr. Tom Rodgers Kurt Nybroe-Nielsen Leif Uldam
Mr. Marvin Schneider B̲j̲a̲r̲n̲e̲ ̲B̲e̲r̲t̲h̲o̲l̲d̲ Per S]ndergaard
Mr. Cavazos Erik Villadsen Jan
Holm
Ole Eskedal
A̲G̲E̲N̲D̲A̲
1 Delivery Status
1.1 Units received by CR
1.2 Units failed in incoming inspection
and use
2 Retrofit actions, schedule
2.1 CPU-baord for 67/73 units
2.2 Sign. I/F-board for 14 units
2.3 Print I/F-board for 14 units
2.4 Bezel for 67/73 units
3 Status on Tempest Evaluation of Changes
4 Status on Documentation. Maintenance
Manual
5 Printer Malfunctions observed by CR
Action
R̲e̲f̲ ̲1̲:̲
1.1 67 printers have been received by
CR. This status complies with the
contract.
Next shipment (6 units 830328) expected
to be on schedule.
1.2 When TRACOR representatives arrived,
status was that 17 units were defective.
When TRACOR representatives departed,
status was that 9 units were defective.
CR expressed their concern about the
high failure rate. Repair needs to
be completed as soon as at all possible
to avoid increasing financial impact
on CR.
Course of actions:
a) Marvin Schneider has established
a complete list of defective items.
TRACOR b) Shipment instructions
for items to
be returned to
TRACOR for repair
will be provided
to CR no later
than Monday 28/3
1983.
TRACOR c) TRACOR will speed
up the repair
process by all
possible means.
Supply to CR
of Spare items
for repair will
be considered.
R̲e̲f̲.̲ ̲2̲:̲
TRACOR expected all retrofit items to
be ready for the April shipment (scheduled
830425).
CR informed that the first batch of printers
will be shipped to the site immediately
after Easter (21 units).
Next shipment from CR to sites will be
in the first week of May.
CR recommended, that all retrofit was
accomplished prior to end of April.
TRACOR TRACOR will investigate if the April
shipment can be advanced, totally
or partly.
R̲e̲f̲.̲ ̲3̲:̲
TRACOR TRACOR promised to keep CR currently
informed on status of Tempest evaluation
of changes.
R̲e̲f̲.̲ ̲4̲:̲
TRACOR informed that the maintenance manual
was being reviewed and delivery was scheduled
to be no later than 15. April 1983.
R̲e̲f̲.̲ ̲5̲:̲
Observed malfunctions.
a) Parity error (light plus print-out).
This error was demonstrated to TRACOR
representatives.
The error pattern was observed to
be influenced by interchange of modules.
TRACOR CR feels that in view of the situation,
where printers are being shipped
to final sites, TRACOR needs to
resolve this problem as fast as
possible.
b) Ribbon lifted out of position by folded
paper.
CR has informed of this malfunction
several times. It is causing operational
non-conformance (complete messages
can be lost).
TRACOR CR requests TRACOR to state their
position on the status and the
options concerning correction
of this malfunction.
c) Paper fold hits metal foil edge at
top of window even after the inside
part has been cut short.
TRACOR TRACOR will provide comment. (Will
this problem be gone, when the
bezel is mounted?).
d) Mounting of Bezel
2 prototypes were delivered to CR
for inspection.
CR has observed that the middle screws
in the side parts seem a little too
short when the washers are left under
the screws or can the washers be left
out. Will longer screws be supplied
as part of the retrofit kit?
TRACOR TRACOR please comment.