C13. Line Item 0009, Terminal Relocation. The Contractor
will provide terminal relocation services and materials
which will allow an installed terminal(s) to be relocated
to anothr room. The Contractor will ensure its operability
and maintain TEMPEST requirements (NACSIM 5100A) after
terminal relocation by the following:
The contractor will make a checkout test of the terminal
relocation, and contractor will make the termnal relocation
installation according to the installation criterias
for the first increment terminals specified in this
proposal.
Contractor will begin a relocation at least 30 DMS
after contractor has received a delivery order.
The relecation ffort will comprise relocation of a
terminal and a walloutlet and installation of the associated
signal cables, connection of the terminal device to
power and signal and checkout of the terminal.
It is assumed that a FCC will provide and install