DataMuseum.dkPresents historical artifacts from the history of: Rational R1000/400 Tapes |
This is an automatic "excavation" of a thematic subset of
See our Wiki for more about Rational R1000/400 Tapes Excavated with: AutoArchaeologist - Free & Open Source Software. |
top - metrics - downloadIndex: B T
Length: 3556 (0xde4)
Types: TextFile
Names: »B«
└─⟦180fe333a⟧ Bits:30000405 8mm tape, Rational 1000, SW CATALOG, 10_20_0
└─⟦180fe333a⟧ Bits:30000537 8mm tape, Rational 1000, SW Catalog 10_20_0
└─⟦5cb1d1d7f⟧ »DATA«
└─⟦3b1ee7bd8⟧
└─⟦this⟧
separate (Tracker.Report_Generator.Calc_Pct_Done)
procedure Get_Ss_Totals is
--------------------------------------------------------------------------------
--|
--| NAME: GET_SS_TOTALS
--|
--| OVERVIEW:
--| This procedure computes the total amount of work, the amount done,
--| and the amount available at start for a subsystem.
--|
--| EXCEPTIONS HANDLED:
--| others error message is printed and execution continues
--|
--| HISTORY:
--| written by Bonnie Burkhardt March 1985
--------------------------------------------------------------------------------
Done : Float range 0.0 .. 999_999.0 := 0.0;
Size : Float range 0.0 .. 999_999.0 := 0.0;
Start : Float range 0.0 .. 999_999.0 := 0.0;
Ele_Start : Float range 0.0 .. 99_999.0;
Ele_Size : Float range 0.0 .. 99_999.0;
Ms_Index : Ms_Num_Type;
begin
-- reset subsystem totals
Ss_Tot_Size := 0.0;
Ss_Tot_Done := 0.0;
Ss_Tot_Start := 0.0;
Ss_Size := (others => 0.0);
Ss_Done := (others => 0.0);
Ss_Start := (others => 0.0);
-- set through each subsystem list and calculate each element
Start_Walk (Ss_Ptr.Element_List);
loop
Walk (Ss_Ptr.Element_List, Ele_Ptr, End_List);
exit when End_List;
Ms_Index := Ele_Ptr.Milestone_Num;
-- compute the size of this element (original or current)
if Orig_Or_Cur = Current then
Ele_Start := Float (Ele_Ptr.Size_Done_At_Start);
Ele_Size := Float (Ele_Ptr.Current_Size) - Ele_Start;
elsif (Ele_Ptr.Original_Size >= Ele_Ptr.Current_Size) or
(Ele_Ptr.Current_Size = 0) then
Ele_Start := Float (Ele_Ptr.Size_Done_At_Start);
Ele_Size := Float (Ele_Ptr.Original_Size) - Ele_Start;
else
Ele_Start := Float (Ele_Ptr.Original_Size) *
Float (Ele_Ptr.Size_Done_At_Start) /
Float (Ele_Ptr.Current_Size);
Ele_Size := Float (Ele_Ptr.Original_Size) - Ele_Start;
end if;
-- add the amount to the running totals for the subsystem
Ss_Tot_Size := Ss_Tot_Size + Ele_Size * Ele_Ptr.Complexity;
Ss_Tot_Start := Ss_Tot_Start + Ele_Start * Ele_Ptr.Complexity;
-- calculate the amount of work done for each activity in the subsystem
-- and for each milestone
Start_Walk (Ac_List);
Ac_Index := 0;
loop
Walk (Ac_List, Ac_Ptr, End_List);
exit when End_List;
Ac_Index := Ac_Index + 1;
Size := Ele_Ptr.Complexity * Ele_Size *
Ac_Ptr.Percent_Tot_Proj / 100.0;
Start := Ele_Ptr.Complexity * Ele_Start *
Ac_Ptr.Percent_Tot_Proj / 100.0;
Done :=
Size * Ac_Pct_Value (Ele_Ptr.Activity_Completeness (Ac_Index)) /
100.0;
Ss_Size (Ac_Index) := Ss_Size (Ac_Index) + Size;
Ss_Start (Ac_Index) := Ss_Start (Ac_Index) + Start;
Ss_Done (Ac_Index) := Ss_Done (Ac_Index) + Done;
Ms_Size (Ms_Index) := Ms_Size (Ms_Index) + Size;
Ms_Done (Ms_Index) := Ms_Done (Ms_Index) + Done;
end loop;
end loop;
-- calculate the total amount of work done
for Ac_Index in 1 .. Num_Of_Activities loop
Ss_Tot_Done := Ss_Tot_Done + Ss_Done (Ac_Index);
end loop;
exception
when others =>
Put_Line ("exception raised in GET_SS_TOTALS.");
end Get_Ss_Totals;